RA Bill & Measurement Book (Excel)

Record every measurement once, in a measurement book with the bill number it belongs to, and the running account bill builds itself. For each item it shows the quantity up to the previous bill, in this bill and up to date, values them at the agreement rate, flags any item that has gone beyond the agreement quantity, and then works out GST, retention money, TDS and the other deductions to reach the net amount payable.

Free · no sign-up · opens in Microsoft Excel, Google Sheets, LibreOffice and WPS Office. Files contain no macros.

Preview

Real view of the file with its sample data (yellow cells are where you type).

Bill summary
RUNNING ACCOUNT BILL No. 2
Construction of G+2 commercial building, Phase 1
EmployerGill Developers Pvt. Ltd.
ContractorSharma Builders & Contractors
Work order / agreementWO/2026/031 dated 19-08-2026
Bill date02-11-2026
Work done during03-10-2026 to 01-11-2026
Gross value of work done up to date₹ 26,58,940.16
Less: value up to previous bill₹ 9,91,993.76
Value of work done in this bill₹ 16,66,946.40
Add: GST @ 18%₹ 3,00,050.35
Bill amount including GST₹ 19,66,996.75
Less: retention money @ 5.0%₹ 83,347.32
Less: income-tax TDS @ 1.0%₹ 16,669.00
Less: GST TDS @ 0.0%₹ 0.00
Less: labour welfare cess @ 1.0%₹ 16,669.00
Less: mobilisation advance recovery₹ 50,000.00
Less: other deductions₹ 0.00
Total deductions₹ 1,66,685.32
NET AMOUNT PAYABLE₹ 18,00,311.00
Rupees Eighteen Lakh Three Hundred Eleven Only
Retention money held up to date (all bills)₹ 1,32,947.01
Value of work done up to date as % of contract value35.6%

What's inside

How to use it

  1. On the Contract sheet type the name of work, the employer, the contractor and the agreement details. Check each deduction rate against your agreement and change it if needed.
  2. On the Items sheet list the agreement items exactly as in the work order: item number, description, unit, agreement quantity and rate.
  3. Each time work is measured, add rows on the MB sheet: date, the bill number the measurement belongs to, the item number, the location and the dimensions. The quantity calculates itself.
  4. When a bill is due, type its number on the Contract sheet (Bill No. for this bill). Measurements with a lower bill number count as "previous", those with this number as "this bill".
  5. Open Bill items to check quantities. Any item shown as Excess has gone beyond the agreement quantity and needs an extra item or variation approval.
  6. Open Bill summary for the net amount payable, print both bill sheets, and get them signed by the contractor, the site engineer and the person approving payment.

Tips

Questions and answers

What is an RA bill?

A running account (RA) bill is a part payment for the work done so far in a long contract. Each RA bill shows the work done up to date, subtracts what was already billed, and pays the difference after deductions. The final bill closes the account.

How does the bill know which measurements are previous?

Every row in the measurement book carries a bill number. Rows with a bill number lower than the current bill are counted as "up to previous bill", rows with the current number as "this bill".

Why is GST added before retention and TDS?

GST is charged on the value of work billed, then the employer makes its deductions from the bill. In this sheet retention, TDS and cess are worked out on the value of work excluding GST, which is the usual practice; change the rates to zero for any deduction that does not apply to your contract.

Can I bill extra items not in the agreement?

Add them on the Items sheet with a new item number (for example EX-1) and an agreement quantity of 0 once they are approved. They will show as Excess until the approved quantity is entered.