Lessons Learned & Closure Report (Word)

Close the project properly: record whether the objectives were met, how the final dates and costs compared with the plan, what was handed over to whom, and the lessons the next project should use. The lessons table is organised by area, with what happened, its effect and a specific recommendation, so the lessons can be acted on rather than filed and forgotten.

Free · no sign-up · opens in Microsoft Word, Google Docs, LibreOffice and WPS Office. Files contain no macros.

Preview

Real view of the file with its sample data (yellow cells are where you type).

PROJECT CLOSURE REPORT AND LESSONS LEARNED

[Project name]

Sponsor[ ]Project manager[ ]
Planned finish[DD-MMM-YYYY]Actual finish[DD-MMM-YYYY]
Report date[DD-MMM-YYYY]Prepared by[ ]

1. Summary

Three or four sentences: what the project delivered, whether it met its objectives, and the most important lesson.

[ ]

2. Objectives achieved

Objective (from the charter)TargetResultMet?
[ ][ ][ ][Yes / Partly / No]
[ ]

3. Schedule and cost

Baseline (plan)ActualDifferenceMain reason
Finish date[ ][ ][ ] days[ ]
Total cost ([currency])[ ][ ][ ][ ]
Approved changes—[number][cost, days][ ]

4. Handover and closure checklist

✓ItemOwner / notes
☐Deliverables accepted and signed off by the sponsor
☐Users trained; user guide handed over
☐Support and maintenance owner agreed
☐Open issues and defects handed over with owners
☐Supplier contracts and purchase orders closed
☐Final invoices paid; project budget closed

5. Lessons learned

One row per lesson. Write a recommendation someone can act on next time, not a complaint.

AreaWhat went wellWhat did not go wellEffectRecommendation
Planning[ ][ ][ ][ ]
Scope and changes
People and roles
Suppliers
Communication
Technology

6. Top three recommendations for the next project

• [ ]

• [ ]

• [ ]

7. Sign-off

RoleNameSignatureDate
Sponsor
Project manager

Guide: a 60-minute lessons learned meeting

Delete this page before you send the report.

…

What's inside

How to use it

  1. Hold the lessons learned meeting within two weeks of the end, while memories are fresh. The guide on the last page gives a 60-minute agenda.
  2. Fill in the objectives table using the measures from the project charter.
  3. Fill in final dates and costs from the Gantt chart and the budget workbook.
  4. Tick the closure checklist and write an owner next to anything still open.
  5. Write the lessons: one row per lesson, with a recommendation someone can act on.
  6. Get the sponsor's sign-off and save the report where the next project manager will find it.

Tips

Questions and answers

When should lessons learned be collected?

At the end of each phase and at the close. Lessons noted only at the very end lose the early details.

Who should attend the lessons learned meeting?

The core team, the sponsor if possible, and key suppliers or users. Six to ten people is a good size.

What is the difference between a closure report and lessons learned?

The closure report records the result (objectives, dates, cost, handover). Lessons learned record what to repeat or change next time. This template holds both.